"Performance feedback on projects" in Dynamics 365 BC - Part 2: Performance feedback via timesheets

Today we want to show you how the Reporting performance on projects It works in Dynamics 365 Business Central. Work on projects can be recorded in the so-called „work time tables“.
To be able to use the work schedules, comparable to timesheets, you first need to assign an admin and a time tracking approver. To do this, simply enter the appropriate resource, i.e., the employee in your company.
Depending on the requirements of your organization, you can specify:

  • One or more users as the timekeeping administrator and approver for all timekeeping systems.
  • A work time schedule approval for each resource.

To create work schedules for a specific period (e.g., month), you can use the batch processing function„Create work schedules“ Use it to create weekly work schedules for all relevant resources (which are defined in advance). After a work schedule has been created, the work schedule owner can open it and report the time required for a task. Based on the resource assignment in the project, the respective work schedule owner can see only the project tasks assigned to them.

The time schedule owner enters the workload for the respective project task on the day of work and clicks „submit“. This will submit his/her work to the time schedule administrator. Depending on your company’s policy, this can, for example, be approved at the end of each week or at the end of the month.
If an invoice is to be prepared at the end of each month, the approved services can be booked at the end of the month.
Learn more about billing in Dynamics 365 Business Central in the July issue of our newsletter!